A port your inbound flow depends on becomes unusable for a fortnight. Walk me through what has to happen to the plans already in flight.
Triage before optimisation: classify what is already committed, what can still be diverted and what has not shipped, then reallocate the scarce alternative capacity by business priority rather than by cost. It only works if your model holds legs and alternates rather than a single route with a port baked into it.