The board asks why engineering has slowed down. What do you measure, and what do you refuse to measure?
Ask what slowed and against what baseline, then bring engineering metrics about the system: where capacity goes, DORA-style delivery and stability measures, flow, and business outcomes. Refuse lines of code, commit counts, cross-team story points and individual rankings, and give every trend its context.
There are forty items left before the release and over the last twelve weeks the team has finished between four and nine a week. The sponsor wants a date. What do you tell them?
Forecast from the whole spread of observed weekly throughput rather than its average, subtract the rate at which the backlog is growing, and give a date with a confidence attached. Then say plainly whether you are offering a forecast or accepting a commitment, because they are not the same promise.
Six months into a scaled agile rollout the sponsor asks whether it is working. What do you measure, and what do you refuse to report?
Report the interval a customer experiences and the quality of what arrives, measured end to end across the programme rather than aggregated from teams. Refuse adoption counts, aggregated velocity and anything that a team can improve by reclassifying its own work.
Which delivery metrics would you actually track for a team, and why does velocity stop working the moment you set a target for it?
Track throughput, cycle-time distribution and flow efficiency, because they describe the system rather than the estimate. Velocity is denominated in a unit the team defines, so making it a target lets the number rise without any change in delivered output, and it stops measuring anything.