When is Scrum the wrong choice for a team, and what would you use instead?

Scrum's Sprint assumes work that can be planned a fortnight ahead, held stable for that fortnight, and shaped into a goal worth committing to. Where one of those fails - interrupt-driven support, single-item research, hard external gates - a flow-based approach fits better.

6 minmid, senior, lead
All 3 in Scrum Framework

Running each event well, keeping standups useful, and facilitating a retrospective that changes something.

All 3 in Facilitation & Ceremonies

Refinement, story splitting, story points versus absolutes, planning poker, and forecasting.

mediumConceptScenario

How do you split a story that is too big to fit in a Sprint?

Split vertically, so each slice goes end to end and delivers something demonstrable, using patterns such as workflow steps, business-rule variations, happy path first, and data or interface variants. Splitting by layer or by half a Sprint is not splitting - it produces work that cannot be reviewed or shipped.

4 minentry, mid, senior
All 3 in Backlog & Estimation

Metrics & Flow

3 questions

Velocity misuse, burndown and burnup, cycle time and CFDs, and Monte Carlo forecasting.

hardScenarioConcept

There are forty items left before the release and over the last twelve weeks the team has finished between four and nine a week. The sponsor wants a date. What do you tell them?

Forecast from the whole spread of observed weekly throughput rather than its average, subtract the rate at which the backlog is growing, and give a date with a confidence attached. Then say plainly whether you are offering a forecast or accepting a commitment, because they are not the same promise.

6 minmid, senior, lead
All 3 in Metrics & Flow

Removing blockers you do not control, protecting the team, and resolving intra-team conflict.

All 3 in Impediments & Conflict

SAFe, LeSS, and Spotify-model claims, plus multi-team dependency and release-train mechanics.

hardDesignScenarioCase Study

You have six teams building one product and they keep blocking each other. How do you coordinate the dependencies, and what do you make of frameworks like SAFe?

Reduce dependencies before coordinating them, by moving team boundaries towards whole slices of value and replacing synchronous handoffs with contracts. Coordinate what remains with a visible dependency board and one ordered backlog. SAFe buys alignment and a planning cadence at real cost in batch size and process.

6 minsenior, staff, lead
hardScenarioCase Study

Two teams build one product and they have different sprint lengths, different boards, different estimation units and different definitions of done. A programme manager wants them standardised. What would you standardise and what would you leave alone?

Very little has to be common, and one thing genuinely does: teams releasing one product must share a Definition of Done. Standardise what a joint release depends on, leave cadence, boards and estimation units local, and refuse uniformity whose only benefit is a comparable dashboard.

6 minsenior, staff, lead
All 3 in Scaling & Frameworks

Scrum Scenarios

3 questions

Situations to work through: a PO who will not prioritise, a team that skips retros, mid-sprint scope injection.

All 3 in Scrum Scenarios