An executive wants a firm date for work your team has not scoped yet. What do you do?
Reject the choice between a fabricated date and no answer. Ask what decision the date serves, separate known work from assumed and unknown work, give a range with its confidence and assumptions attached, buy the missing information with a timeboxed spike, and offer to fix scope or date but not both.