Browse 3 real-world technical and behavioral interview questions about Execution. Review scenarios, edge cases, and architectural best practices.
Find out what the date is being used for, then commit to something you can actually control — a timeboxed discovery end, a date for the date, or a narrow first slice — and never issue a single-point estimate for scope that is still undefined.
Find out what the six weeks is made of before negotiating anything, then choose between cutting scope, splitting the release, launching to a limited cohort and moving the date — and tell everyone who depends on the date the same day you know.
Re-plan around the dependency before you escalate: price the delay, find the smallest thing the other team could give you, and design a version that ships without them. Escalate only with a costed choice between two named options, and never as a complaint about the other team's judgement.