Browse 3 real-world technical and behavioral interview questions about Velocity. Review scenarios, edge cases, and architectural best practices.
Treat four misses as data about the system rather than a verdict on the team: find out whether the goal is set by the team or handed to it, whether unplanned work arrives mid-sprint, and whether done is being deferred, then fix the cause you find instead of shrinking the commitment.
Track throughput, cycle-time distribution and flow efficiency, because they describe the system rather than the estimate. Velocity is denominated in a unit the team defines, so making it a target lets the number rise without any change in delivered output, and it stops measuring anything.
Points are relative sizes that trade false precision for a fast conversation whose real output is surfaced disagreement. Estimates that are always wrong are a system symptom, so diagnose unclear criteria, oversized stories, invisible work and interruptions, then forecast with throughput and cycle time.