There are forty items left before the release and over the last twelve weeks the team has finished between four and nine a week. The sponsor wants a date. What do you tell them?

Forecast from the whole spread of observed weekly throughput rather than its average, subtract the rate at which the backlog is growing, and give a date with a confidence attached. Then say plainly whether you are offering a forecast or accepting a commitment, because they are not the same promise.