You have six teams building one product and they keep blocking each other. How do you coordinate the dependencies, and what do you make of frameworks like SAFe?
Reduce dependencies before coordinating them, by moving team boundaries towards whole slices of value and replacing synchronous handoffs with contracts. Coordinate what remains with a visible dependency board and one ordered backlog. SAFe buys alignment and a planning cadence at real cost in batch size and process.