For three sprints running your team has lost most of a week waiting for a shared test environment another group controls. What do you do about it?
Price the delay in developer-days from the board's own timestamps, then escalate with a specific ask, an owner and a date rather than a complaint. Decide honestly whether this is an impediment somebody can remove or a constraint to design around, and watch for the workaround that hides the cost.